UPDATED 1 Sept: The EI library in London is temporarily closed to the public, as a precautionary measure in light of the ongoing COVID-19 situation. The Knowledge Service will still be answering email queries via email , or via live chats during working hours (09:15-17:00 GMT). Our e-library is always open for members here: eLibrary , for full-text access to over 200 e-books and millions of articles. Thank you for your patience.

Comparing decommissioning costs – NW Europe versus SE Asia

Platforms may be similar in characteristics and configuration, but the cost of decommissioning them can differ significantly depending on location, climate and regulations.

In its most recent analysis, Rystad Energy estimates that the cost of removing a steel platform in the North Sea, excluding subsea infrastructure, is above twice the cost of the same task in Southeast Asia. The study is based on two similar steel platforms, one in each region, located in 60 metres of water with four piles, a topside weight of 1,500 tonnes and a jacket weight of 800 tonnes.

Facility removal for the platform described above would cost $22.35mn in the North Sea, comparing to just $9.08mn in Southeast Asia, mainly driven by the higher spread rates as well as weather conditions which can represent a significant operational challenge, according to the market analyst. The removal costs include elements such as heavy lift vessels, support barges and tugs, and cutting and diving crews, which would be mobilised to the fields for the decommissioning operation. The entire topsides would be removed in one piece, with Rystad accounting for a heavy lift vessel with sufficient lifting capacity.

The substructure removal is the costliest phase of the demolition process. It depends on several factors such as the age of the platform, water depth, climate conditions, structure weight, the number of lifts required and the number of piles. For this study, as the structure is located in less than 100 metres of water and weighs less than 2,000 tonnes, it has been assumed that the four piles would be cut below the seabed and the structures would be removed in a single lift. The structures would then be transported to shore for disposal using a transport barge.

For the Southeast Asian field, a derrick barge with a 2,000-tonne lift capacity would be mobilised from Singapore, requiring two days to reach the field’s location. In the North Sea, a dynamic positioning vessel would be required instead of a derrick barge, as it is better suited to the volatile winds and waves in the region.

The day rates for a dynamic positioning heavy lift vessel are on average more than 50% higher than for a derrick barge with the same lifting capacities. To estimate the same mobilisation time, Rystad has assumed that a dynamic positioning vessel would be mobilised from Rotterdam and require two days to reach the field, but it is worth noting that mobilisation from farther away is not uncommon in this region.

‘The removal cost per platform can also vary within the same region depending on the time and scale of the decommissioning campaign. Removing multiple facilities at the same time can help optimise costs by spreading the mobilisation and demobilisation costs across different assets,’ says Sara Sottilotta, Energy Service Analyst in Rystad Energy.

In addition, flexibility around timing can allow for more attractive rates. Rystad expects vessel rates to hit bottom in 2021 before starting to rise again. As the material disposal cost is heavily dependent on the price of steel, flexibility around the disposal time could help bring down costs further by waiting to dispose of the steel until steel prices are high.

With more than 280 assets approaching the end of their lifetime, Southeast Asia faces a surge in decommissioning in the years ahead. Most of the offshore platforms due to be retired in the region at present have less than 3,000 topside tonnes and are located in less than 75 metres of water.

Most Southeast Asian countries do not have fully developed decommissioning legislation in place, and decommissioning projects are therefore dealt with on a case-by-case basis. For example, Petronas implemented a rigs-to-reef solution for two platforms at the Dana and D-30 fields off the coast of Malaysia in 2017.

On the other hand, the North Sea represents a more mature market where regulations governing the removal of offshore structures are more formalised and consolidated. Consistent with the OSPAR Decision 98/3, facilities have to be fully removed in the North Sea. This prohibits dumping or leaving in place disused offshore installations, effectively requiring that they are completely removed to be reused, recycled, or disposed of on land.

For more on decommissioning in the North Sea, see
Petroleum Review’s October 2020 issue.