New Energy World magazine logo
New Energy World magazine logo
ISSN 2753-7757 (Online)

UK government refuses permission for 840MW solar farm near Oxford

17/11/2026

News

Large green field captioned 'application refused' Photo: Stop Botley West
Screen grab of website of campaign group Stop Botley West after the project was denied a development consent order by the UK government

Photo: Stop Botley West

Plans for an 840MW solar farm, one of the UK’s biggest, to be built in three sections west and northwest of the city of Oxford, have been refused at the development consent stage.

A decision letter published by the Secretary of State Miatta Fahnbulleh ruled that the project would create ‘substantial harm’ to Green Belt land, designated heritage assets, most notably Blenheim Palace, as well as have significant adverse effects on the landscape, visual amenity, and aviation safety at Oxford Airport in Kidlington.

 

In summary, she concluded that the impact of the proposed development would outweigh its benefits as a source of renewable energy, even though building renewable energy has been designated a ‘critical national priority’.

 

A particular objection of the government was that in focusing on the development’s value as renewable energy the developers had not taken sufficiently seriously the UK planning approach to mitigating the potential harm of development.

 

The report said: ‘In particular, the Secretary of State is not satisfied that the Applicant has demonstrated that the mitigation hierarchy has been appropriately applied in respect of landscape and visual, aviation, good design, ecology and biodiversity, mineral resources and cultural heritage matters.’

 

According to the UK Green Building Council, the mitigation hierarchy involves a rigid sequence of four steps starting with ‘avoid’ (evade or reduce biodiversity impacts through site selection and layout), then ‘minimise’ (measures to reduce the extent of impact), then ‘mitigate’ (on-site habitat or affected area is improved and/or protected), then ‘offset’ (compensate loss).

 

The developer, Berlin-based Photovolt Development Partners, worked on the project on behalf of SolarFive, which holds the connection agreement with National Grid and is licensed by the Office of Gas and Electricity Markets (Ofgem) as an electricity generator.

 

It began early engagement work in September 2022. According to the government, more than 1,000 representations were made on the project, including a flurry of late work over 2026 after the examining officer’s report was completed early in the year.

 

Photovolt Development Partners lists about 400MW of combined operating solar farms at four sites in Japan, plus a 480MWp site under construction in Ukujima and Terajima, Japan.

 

A local campaign group, Stop Botley West, posted a short note on its website saying it was pleased with the result and congratulating its supporters.