UPDATED 1 Sept: The EI library in London is temporarily closed to the public, as a precautionary measure in light of the ongoing COVID-19 situation. The Knowledge Service will still be answering email queries via email , or via live chats during working hours (09:15-17:00 GMT). Our e-library is always open for members here: eLibrary , for full-text access to over 200 e-books and millions of articles. Thank you for your patience.

Hinkley Point C second reactor base

Work on the 49,000-tonne base for the second reactor at EDF Energy’s Hinkley Point C (HPC) has been completed on schedule.

Hanson UK supplied the raw materials for the concrete to main civils contractor BYLOR, which operates the on-site concrete production plant at the nuclear power station under construction in Somerset.

A four-day, 9,000 m3 continuous reinforced structural concrete pour marked completion of the ‘common raft’ for HPC’s second reactor – the reinforced concrete platform on which the reactor, and other parts of the nuclear island sit.

Completion of the base marks the transition from below ground activity to the construction of permanent reactor buildings above ground.